Maintenance Criteria for Pavements and Structures - National Highways Authority of India

National Highways Authority of India

Table 1: Maintenance Criteria for Pavements

Asset Type Performance Parameter Desirable Acceptable Frequency of Inspection Tools/Equipment Standards and References for Inspection and Data Analysis Time limit for Rectification / Repair Maintenance specifications
Flexible Pavement Routine Inspection (Pavement of MCW, Service Road, Approach of Grade structures, approaches of connecting roads, slip roads, lay byes etc. as applicable) Potholes Nil <0.1% of area and subjected to limit of 10mm in depth Daily Length Measurement Unit like Scale, Tape, odometer etc. MORT&H 24-48 hours MORT&H Specification 3004.2
Cracking Nil <5% subject to limit of 0.5 sqm for any 50m length Daily 7-15 days MORT&H Specification 3004.3
Rutting Nil <5mm Daily Straight Edge IRC 82: 2015 and 15-30 days MORT&H Specification 3004.2
Corrugations and Shoving Nil 0.1% of area Daily Length Measurement Distress Identification Manual for Long Term Pavement Performance Program, FHWA 2003 2-7 days IRC:82-2015
Bleeding Nil <1% of area Daily Unit like Scale, Tape, odometer etc. 3-7 days MORT&H Specification 3004.4
Ravelling/ Stripping Nil <1% of area Daily Length Measurement Unit like Scale, Tape, odometer etc. 7-15 days IRC:82-2015 read with IRC SP-81
Edge Deformation / Breaking Nil and/or width <0.1m at any Location restricted to 30cm from the edge. <1m for any 100m section Daily 7-15 days IRC:82-2015
Roughness 2000 mm/km 2400 mm/km Bi-Annually Network Survey vehicle (NSV) with all its module such as Laser Profilometers, Transverse profile logger, Laser crack measurement system, Video logging modules, high resolution Odometer etc. ASTM E950 (98) :2004 Standard Test Method for measuring Longitudinal Profile of Travelled Surfaces with Accelerometer Established Inertial Profiling Reference and ASTM E1656 -94:2000- Standard Guide for Classification of Automatic Pavement Condition Survey Equipment 180 days IRC:82-2015
Rutting <10mm for any 50 m section and/or, length of section <5m <10mm for any 50 m section and/or, length of section <10m Bi-Annually 15-30 days IRC:82-2015
Pavement rating based on distress per IRC 82 / Pavement Condition Index as per ASTM 6433-07 >3/85 >2.1/70 Bi-Annually 180 days IRC:82-2015/ ASTM D 6433-07
Flexible Pavement Programmed Inspection Other Pavement Distresses - - Bi-Annually 2-7 days IRC:82-2015
Skid 60SN 50SN Bi-Annually SCRIM (Sideway force Coefficient Routine Investigation Machine or equivalent) British Pendulum Tester BS:7941-1:2006, IRC:82-2015/ ASTM 274 180 days IRC:82-2015
Deflection/ Remaining Life - Annually Falling Weight Deflectometer IRC 115: 2014 180 days IRC:115-2014
Rigid Pavement (Pavement of MCW, Service Road, Grade separated structure, approaches of connecting roads, slip roads, lay byes etc. as applicable. Roughness BI <2200mm/km <2400mm/km Bi-Annually Class I Profilometer Mounted on NSV ASTM E950 (98) :2004 and ASTM E1656 -94: 2000 180 days IRC: SP:83-2018
Skid Skid Resistance No. at different speed of vehicles Minimum SN Traffic Speed 36 50 33 65 32 80 31 95 31 100 Bi-Annually SCRIM (Sideway force Coefficient Routine Investigation Machine or equivalent) British Pendulum Tester 180 days IRC: SP:83-2018
Embankment /Slope Edge drops at shoulders Nil 40mm Daily Length Measurement Unit like Scale, Tape, odometer etc. IRC 7-15 days MORT&H Specification
Slope of camber/cross fall Nil <2% variation in prescribed slope of camber /cross fall Daily 7-15 days MORT&H Specification
Embankment Slopes Nil <15 % variation in prescribe side slope Daily 7-15 days MORT&H Specification
Embankment Protection Nil Nil Daily NA 7-15 days MORT&H Specification
Rain Cuts/Gullies in slope Nil Nil Daily Specially During Rainy Season NA IRC 7-15 days MORT&H Specification
Cut Section/ Slope Unstable Slopes Nil - NA IRC 2-7 days MORT&H Specification

Table 2: Maintenance Criteria for Rigid Pavements

S. No Type of Distress Measured Parameter Degree of Severity Assessment Rating Repair Action
For the case d < D/2 For the case d > D/2
CRACKING 1 Single Discrete Cracks Not intersecting with any joint or Single Transverse (or Diagonal) Crack intersecting with one or more joints w = width of crack, L = length of crack, d = depth of crack, D = depth of slab 0 Nil, not discernible No Action -
1 w < 0.2 mm. hair cracks Seal without delay Full Depth Repair Dismantle and reconstruct affected portion - See Para 5.4, within 15 days
2 w = 0.2 - 0.5 mm, discernible from slow-moving car
3 w = 0.5 - 1.5 mm, discernible from fast-moving car Seal and stitch if L > l m. within 7 days
4 w = 1.5 - 3.0 mm
5 w > 3 mm.
2 Single Transverse (or Diagonal) Crack intersecting with one or more joints w = width of crack L = length of crack d = depth of crack D = depth of slab 0 Nil, not discernible No Action
1 w < 0.2 mm. hair cracks Route and seal with Epoxy within 7 days Seal Staple within 15days & Cross stich or
2 w = 0.2 - 0.5 mm, discernible from slow-moving car
3 w = 0.5 3.0 mm, discernible from fast-moving car Seal and stitch, if L > l m. within 7 days Full Depth Repair Dismantle and reconstruct affected portion with norms & Specifications - See Para 5.5 &refer chapter 9 of IRC: SP: 83-2018, within 15 days.
4 w = 3.0 - 6.0 mm Not Applicable Staple or Dowel Bar Retrofit within 15 days.
5 w > 6 mm, usually associated with spalling, and/or slab rocking under traffic Not Applicable, (full depth crack) Staple or Dowel Bar Retrofit within 15 days
3 Single Longitudinal Crack intersecting with one or more joints w = width of crack L = length of crack d = depth of crack D = depth of slab 0 Nil, not discernible No Action
1 w < 0.5 mm, discernable from slow moving vehicle Seal and stich if L >l m within 7 days Seal and Cross-Stich or Staple within 15 days
2 w = 0.5 - 3.0 mm, discernible from fast vehicle Seal & Staple, within 15 days Partial Depth Repair with or without dowel bar retrofit within 15 days or
3 w = 3.0 - 6.0 mm
4 w = 6.0 - 12.0 mm, usually associated with spalling Not applicable
5 w > 12 mm, usually associated with spalling, and/or slab rocking under traffic Not Applicable, (Rocking/ Spalling indicates full depth crack) Full Depth Repair Dismantle and reconstruct affected portion - See Fig 5.6 and Chapter 9 of IRC: SP:83-2018, within 15 days
4 Multiple Cracks intersecting with one or more joints w = width of crack 0 Nil, not discernible No Action
1 w < 0.2 mm. hair cracks Seal and stitch if L > l m. within 15 days Dismantle and Reconstruct whole slab as per Specifications within 30days.
2 w = 0.2 - 0.5 mm, discernible from slow-moving car
3 w = 0.5 3.0 mm, discernible from fast-moving car Full depth repair within 15 days
4 w = 3.0 - 6.0 mm panel broken into 2 or 3 pieces Reinstate sub- base, reconstruct whole slab within 30days.
5 w > 6 mm and/or panel broken into more than 4 pieces
5 Corner Break w = width of crack, L = length of crack 0 Nil, not discernible No Action
1 w < 0.5 mm; only 1 corner broken Seal with low viscosity epoxy to secure broken parts within 7 days
2 w < 1.5 mm; L < 0.6 m, only one corner broken Partial Depth (Refer Figure 8.3 of IRC: SP:83-2018) within 15 days
3 w < 1.5 mm; L < 0.6 m, two corners broken
4 w > 1.5 mm; L > 0.6 m or three corners broken Full depth repair within 30 days.
5 three or four corners broken Reinstate sub-base, and reconstruct the slab as per norms & Specifications within 30 days.
6 Punchout (Applicable to Continuous Reinforced Concrete Pavement CRCP only) w = width of crack L = length (m/m2) 0 Nil, not discernible No Action Not Applicable, (Punch-out is full depth Distress)
1 w < 0.5 mm; L < 3 m/m2 Full depth repair - Cut out and replace damaged area taking care not to damage reinforcement. Within 30 days. Seal with low viscosity epoxy to secure broken parts Within 15 days
2 either w > 0.5 mm or L < 3 m/m2
3 w > 1.5 mm and L < 3 m/m2
4 w > 3 mm, L < 3 m/m2 and deformation
5 w > 3 mm, L > 3 m/m2 and deformation
Surface Defects 7 Ravelling or Honeycomb type surface r = area damaged surface/total surface of slab (%) h = maximum depth of damage 0 Nil, not discernible No action. Not Applicable
1 r < 2 % Local repair of areas damaged and liable to damage. Within 15 days
2 r = 2 - 10 %
3 r = 10-25% Bonded Inlay, if affecting 2 or 3 slabs. Within 30 days
4 r = 25 - 50 %
5 r > 50% and h > 25 mm Reconstruct slabs, if affecting 4 or more slabs. Within 30 days
8 Scaling r = area damaged surface/total surface of slab (%) h = maximum depth of damage 0 Nil, not discernible No action. Not Applicable
1 r < 2 % Local repair of areas damaged and liable to within 7 days
2 r = 2 - 10 % Bonded Inlay within 15 days
3 r = 10 - 20%
4 r = 20 - 30 %
5 r > 30 % and h > 25 mm Reconstruct slab within 30 days.
9 Polished Surface/Glazing t = texture depth, sand patch test 0 No action. Not Applicable
1 t > 1 mm Monitor rate of deterioration
2 t = 1 - 0.6 mm
3 t = 0.6 - 0.3 mm
4
5 t < 0.3 mm Diamond Grinding if affecting 50% or more slabs in a continuous stretch of minimum 5 km. Within 30 days
10 Popout (Small Hole), Pothole Refer Para 8.4 n = number/m2, d = diameter, h = maximum depth 0 d < 50 mm; h < 25 mm; n < 1 per 5 m2 No action. Not Applicable
1 d = 50 - 100 mm; h < 50 mm; n < 1 per 5 m2 Partial depth repair 65 mm deep. Within 15 days
2 d = 50 - 100 mm; h > 50 mm; n < 1 per 5 m2
3 d = 100 - 300 mm; h < 100 mm n < 1 per 5 m2 Partial depth repair 110mm i.e.,10 mm more than the depth of the hole within 30 days
4 d = 100 - 300 mm; h > 100 mm; n < 1 per 5 m2
5 d > 300 mm; h > 100 mm: n > 1 per 5 m2 Full depth repair within 30 days.
JOINT DEFECT 11 Joint Seal Defects loss or damage L = Length as % total joint length 0 Difficult to discern. No action.
1 Discernible, L< 25% but of little immediate consequence with regard to ingress of water or trapping incompressible material. Clean joint, inspect later. Not Applicable
3 Notable. L > 25% insufficient protection against ingress of water and trapping Clean and reapply sealant in selected locations. Within 7 days. Not Applicable
5 Severe; w > 3 mm negligible protection against ingress of water and trapping incompressible material. Clean, widen and reseal the joint following strict procedures within 7 days.
12 Spalling of Joints w = width on either side of the joint L = length of spalled portion (as % joint length) 0 Nil, not discernible No action.
1 w < 10 mm Apply low viscosity epoxy resin/mortar in cracked portion within 7 days
2 w = 10 - 20 mm, L < 25%
3 w = 20 - 40 mm, L > 25% Partial Depth Repair, 30 - 50 mm deep, h = w+ 20% of w, within 30 days
4 w = 40 - 80 mm, L > 25%
5 w > 80 mm, and L > 25% 50 - 100 mm deep repair. H = w + 20% of w, within 30 days
13 Faulting (or Stepping) in Cracks or Joints f = difference of level 0 not discernible, < 1 mm No action.
1 f < 3 mm
2 f = 3 - 6 mm Determine cause and observe
3 f = 6 - 12 mm Diamond Grinding within 15 days
4 f= 12 - 18 mm Raise sunken slab within 15 days.
5 f> 18 mm Strengthen subgrade and sub-base by grouting, within 30 days.
14 Blowup or Buckling h = vertical displacement from normal profile 0 Nil, not discernible No action.
1 h < 6 mm Install Signs to Warn Traffic, within 24 hours days
2 h = 6 - 12 mm
3 h = 12 - 25 mm
4 h > 25 mm Full Depth Repair, within 30 days.
5 shattered slabs, i.e. 4 or more pieces Replace broken slabs, within 30 days.
15 Depression h = negative vertical displacement from normal profile. L = length 0 Not discernible. h < 5 mm No action.
1 h = 5 - 15 mm Install Signs to Warn Traffic, within 24 hours
2 h = 15 - 30 mm, Nos<20% joints
3 h = 30 - 50 mm
4 h > 50 mm or > 20% joints Strengthen subgrade. Reinstate pavement at normal level, within 30 days.
5 h > 100 mm
16 Heave h = positive vertical displacement from normal profile. L = length 0 Not discernible. h < 5 mm No action.
1 h = 5 - 15 mm Follow up.
2 h = 15 - 30 mm, Nos<20% joints Install Signs to Warn Traffic, within 24 hours
3 h = 30 - 50 mm
4 h > 50 mm or > 20% joints Stabilise subgrade. Reinstate pavement at normal level, within 30 days
5 h > 100 mm
17 Bump h = vertical displacement from normal profile 0 No action.
1 h = 4 - 7 mm Grind, in case of new construction. Within 7 days
3 h = 7 - 15 mm Grind in case of Ongoing maintenance within 15 days
5 h > 15 mm
18 Lane to Shoulder Drop- off f = difference of level 0 not discernible < 3mm No action.
1 f = 3 - 10 mm Spot repair of shoulder. Within 3 days
2 f = 10 - 25 mm
3 f = 25 - 50 mm Fill up shoulder within 7 days
4 f = 50 - 75 mm For any 100 m segment, Reconstruct shoulder, if affecting 25% or more of segment, within 30 days.
5 f > 75 mm
DRAINAGE 19 Pumping quantity of fines and water expelled through open joints and cracks Nos/100 m stretch 0 not discernible No action.
1 to 2 slight/occasional Nos< 10% Repair cracks and joints without delay Inspect and repair Sub-drainage at distressed sections and upstream
3 to 4 appreciable/Frequent 10 - 25% Lift or jack slab within 30 days.
5 abundant, crack development > 25% Repair distressed pavement sections. Strengthen subgrade And sub-base. Replace slab. Within 30 days.
20 Ponding Ponding on slabs due to blockage of drains 0-2 No discernible problem No action. Action required to stop water damaging foundation within 15 days.
3 to 4 Blockages observed in drains, but water flowing Clean drains etc., follow up, deep groving in transverse direction to remove
5 Ponding, accumulation of water observed Deep groving in transverse direction to remove water-hydro planning within 7 days

Table 3: Maintenance Criteria for Safety Related Items and Other Furniture Items

Asset Type Performance Parameter Level of Service (LOS) Design Speed (kmph) Desirable Minimum Sight Distance (m) Safe Stopping Sight Distance (m) Frequency of Measurement Testing Method Recommended Remedial Measures Time limit for Rectification Specifications and Standards
Highway Availability of Safe Sight Distance As per IRC SP:84-2019, a minimum of safe stopping sight distance shall be available throughout. 100 360 180 Monthly Manual Measurements With Odometer along with video/ image backup Removal of obstruction within 24 hours, in case of sight line affected by temporary objects such as trees, temporary encroachments. In case of permanent structure or design deficiency: * Removal of obstruction/ improvement of deficiency at the earliest * Speed Restriction boards and suitable traffic calming measures such as transverse bar marking, blinkers, etc. shall be applied during the period of rectification. IRC: SP:84-2019
80 260 130
Pavement Marking Wear <70% of marking remaining Bi-Annually Visual Assessment as per Annexure- F of IRC:35-2015 Re-Painting Cat-1 Defect within 24 hours Cat-2 Defect within 2 months IRC:35-2015
Day time Visibility During expected life Service Time - 130mcd/m2/lux - 100mcd/m2/lux Monthly As per Annexure- D of IRC:35- 2015 Re-Painting Cat-1 Defect within 24 hours Cat-2 Defect within 2 months IRC:35-2015
Night Time Visibility Initial and Minimum Performance for Dry Retro reflectivity during night time: Design Speed (RL) Retro-Reflectivity (mcd/m²/lux) Initial (7Days) Minimum Threshold Level and warranty period required up to 2 years (TL) Bi-Annually As per Annexure-E of IRC:35- 2015 Re-Painting Cat-1 Defect within 24 hours Cat-2 Defect within 2 months IRC:35-2015
Up to 65 200 80
65 - 100 250 120
above 100 350 150
Initial and Minimum Performance for Night Visibility under wet condition (Retro reflectivity): mcd/m2/lux mcd/m2/lux
Skid Resistance Initial and Minimum performance for Skid Resistance *Note: shall be considered under urban/city traffic condition encompassing the locations like pedestrian crossings, bus bay, bus stop, cycle track intersection delineation, transverse bar markings etc. Bi-Annually As per Annexure-G of IRC:35- 2015 Within 24 hours IRC:35-2015
Road Sign Shape and Position Shape and Position as per IRC:67- 2012. Signboard should be clearly visible for the design speed of the section Daily Visual with video/image backup Improvement of shape, in case if shape is damaged. Relocation as pe requirement 48 hours in case of Mandatory Signs, Cautionary and Informatory Signs (Single and Dual post signs), 15 Days in case of Gantry/ Cantilever Sign boards IRC:67-2012
Retro reflectivity As per specifications in IRC:67-2012 Bi-Annually Testing of each signboard using Retro Reflectivity Measuring Device. In accordance with ASTM D 4956-09 Change of signboard 48 hours in case of Mandatory Signs, Cautionary and Informatory Signs (Single and Dual post signs). 1 Month in case of Gantry/ Cantilever Sign boards IRC:67-2012
Kerb Kerb Height As per IRC 86:2018 depending upon type of Kerb Bi-Annually Use of distance measuring tape Raising Kerb Height Within 1 Month IRC 86:2018
Kerb Painting Functionality Functioning of Kerb painting as intended Daily Visual with video/image backup Kerb Repainting Within 7-days IRC 35:2015
Other Road Furniture Reflective Pavement Markers (Road Studs) Numbers and Functionality as per specifications in IRC: SP:84-2019 and IRC:35-2015, unless specified in Schedule-B. Daily Counting New Installation Within 2 months IRC: SP:84-2019, IRC:35-2015
Pedestrian Guardrail Functionality Functioning of guardrail as intended Daily Visual with video/image backup Rectification Within 15 days IRC: SP:84-2019
Traffic Safety Barriers Functionality Functioning of Safety Barriers as intended Daily Visual with video/image backup Rectification Within 7-days IRC: SP:84-2019, IRC:119-2015
End Treatment of Traffic Safety Barriers Functionality Functioning of End treatment as intended Daily Visual with video/image backup Rectification Within 7-days IRC: SP:84-2019, IRC:119-2015
Attenuators Functionality Functioning of Attenuators as intended Daily Visual with video/image backup Rectification Within 7-days IRC: SP:84-2019, IRC:119-2015
Guard Posts and Delineators Functionality Functioning of Guard Posts and Delineators as intended Daily Visual with video/image backup Rectification Within 15 days IRC:79-2019
Overhead Sign Structure Overhead sign structure shall be structurally adequate Daily Visual with video/image backup Rectification Within 15 days IRC:67-2012
Traffic Blinkers Functionality Functioning of Traffic Blinkers as intended Daily Visual with video/image backup Rectification Within 7-days days IRC: SP:84-2019
Highway Lighting System Highway Lights Illumination: Minimum 40 Lux illumination on the road surface Daily The illumination level shall be measured with lux- meter Improvement in Lighting System 24 hours IRC: SP:84-2019
No major failure in the lighting system Daily - Rectification of failure 24 hours IRC: SP:84-2019
No minor failure in the lighting system Monthly - Rectification of failure IRC: SP:84-2019
Toll Plaza Canopy Lights Minimum 40 Lux illumination on the road surface Daily The illumination level shall be measured with lux- meter Improvement in Lighting System 24 hours IRC: SP:84-2019
No major/minor failure in the lighting system Daily Rectification of failure 8 hours IRC: SP:84-2019
Trees and plantation including median plantation Obstruction in a minimum head- room of 5.5 m above carriageway or obstruction in visibility of road signs Monthly Visual with video/image backup Removal of trees Immediate IRC: SP:84-2019
Deterioration in health of trees and bushes Daily Visual with video/image backup Timely watering and treatment. Or Replacement of Trees and Bushes. Within 90 days IRC: SP:84-2019
Vegetation affecting sight line and road structures Daily Visual with video/image backup Removal of trees Immediate IRC: SP:84-2019
Rest Area Cleaning of toilets Daily - - Every 4 hours -
Defects in electrical, water and sanitary installations Daily - Rectification 24 hours -
Other Project Facilities and Approach roads Damage or deterioration in Approach Roads, pedestrian facilities, truck lay-bys, bus-bays, bus-shelters, cattle crossings, Traffic Aid Posts, Medical Aid Posts, and other works Daily - Rectification 15 Day IRC: SP:84-2019

Table 4: Maintenance Criteria for Structures and Culverts

Asset Type Performance Parameter Level of Service (LOS) Frequency of Measurement Testing Method Recommended Remedial measures Time limit for Rectification Specifications and Standards
Pipe/box/slab culverts Free waterway/ unobstructed flow section 85% of culvert normal flow area to available. 2 times in a year (before and after rainy season) Inspection by Bridge Engineer as per IRC SP: 35- 1990 and recording of depth of silting and area of vegetation Cleaning silt up soils and debris in culvert barrel after rainy season, removal of bushes and vegetation, U/s of barrel, under barrel and D/s of barrel before rainy season. 15 days before onset of monsoon and within 30 days after end of rainy season. IRC 5-2015, IRC SP:40-2019 and IRC SP:13-2004
Leak-proof expansion joints if any No leakage through expansion joints Bi-Annually Physical inspection of expansion joints as per IRC SP: 35- 1990 if any, for leakage strains on walls at joints. Fixing with sealant suitably 30 days or before onset of rains whichever comes earlier IRC SP:40-2019 and IRC SP:69-2011
Structurally sound Spalling of concrete not more than 0.25 sq.m. Bi-Annually Detailed inspection of all components of culvert as per IRC SP:35-1990 and recording the defects Repairs to spalling, cracking, delamination, rusting shall be followed as per IRC: SP:40-2019. 15 days IRC SP 40-2019 and MORTH Specifications clause 2800
Delamination of concrete not more than 0.25 sq.m.
Cracks wider than 0.3 mm not more than 1m aggregate length
Protection works in good condition Damaged of rough stone apron or bank revetment not more than 3 sq.m, damage to solid apron (concrete apron) not more than 1 sq.m 2 times in a year (before and after rainy season) Condition survey as per IRC SP:35-1990 Repairs to damaged aprons and pitching 30 days after defect observation or 2 weeks before onset of rainy season whichever is earlier. IRC: SP 40-2019 and IRC SP:13-2004
Bridges including Flyover and Viaducts etc. as applicable Riding quality No pothole in wearing coat on bridge deck Daily Visual inspection as per IRC SP:35-1990 Repairs to BC or wearing coat 15 days MORT&H Specification 2811
Bumps No bump at expansion joint Daily Visual inspection as per IRC SP:35-1990 Repairs to BC on either side of expansion joints, profile correction course on approach slab in case of settlement to approach embankment 15 days MORT&H Specification 3004.2 & 2811
Bridges including Flyover and Viaducts etc. -Super Structure User safety (condition of crash barrier and guard rail) No damaged or missing stretch of crash barrier or pedestrian hand railing Daily Visual inspection and detailed condition survey as per IRC SP: 35-1990 Repairs and replacement of safety barriers as the case may be 3days IRC: 5-2015, IRC SP: 84-2019 and IRC SP: 40- 2019
Rusted reinforcement Not more than 0.25 sq.m Bi-Annually Detailed condition survey as per IRC SP: 35-1990 using Mobile Bridge Inspection unit. Repairs to spalling, cracking, delamination, rusting shall be followed as per IRC: SP:40-2019. 15 days IRC SP: 40-2019 and MORTH Specification 2800
Spalling of concrete Not more than 0.50 sq.m
Delamination Not more than 0.50 sq.m
Cracks wider than 0.30 mm Not more than 1m total length
Rainwater seepage through deck slab Leakage - nil
Deflection due to permanent loads and live loads Within design limits. Once in every 10 years for spans more than 40 m Load test method Carry out major rehabilitation works on bridge to retain original design loads 6 months IRC SP: 51-2015
Vibrations in bridge deck due to moving trucks Frequency of vibrations shall not be more than 5 Hz Once in every 5 years for spans more than 30m and every 10 years for spans between 15 to 30 Laser displacement sensors or laser vibro- meters Strengthening of super structure 4 months AASHTO, LRFD specifications
Bridges including Flyover and Viaducts etc. -Super Structure Leakage in Expansion joints No damage to elastomeric sealant Bi-Annually Detailed condition survey as per IRC SP: 35-1990. using Mobile Bridge Inspection Unit. Replacement of seal in expansion joint. Replacement of Sealing compound in case of leakage I case of copper strip type joint. 15 days MORTH specifications 2600, IRC SP: 40- 2019.
Debris and dust in strip seal expansion joint No dust or debris in expansion joint gap. Monthly Detailed condition survey as per IRC SP: 35-1990. using Mobile Bridge Inspection Unit. Cleaning of expansion joint gaps thoroughly 3 days MORTH specifications 2600, IRC SP: 40-2019 and IRC: SP:69-2011
Drainage spouts No down take Pipe missing/broken below soffit of the deck slab. No silt, debris, clogging of drainage spout collection chamber. Monthly Detailed condition survey as per IRC SP: 35-1990. using Mobile Bridge Inspection Unit. Cleaning of drainage spouts thoroughly. Replacement of missing/broken down take pipes with a minimum pipe extension of 500mm below soffit of slab. Providing sealant around the drainage spout if any leakages observed. 3 days MORTH specification 2700
Cracks/ spalling of concrete /rusted steel No cracks, spalling of concrete and rusted steel Bi-Annually Detailed condition survey as per IRC SP:35-1990 using Mobile Bridge Inspection Unit. All the corroded reinforcement shall need to be thoroughly cleaned from rusting and applied with anti- corrosive coating before carrying out repairs to substructure by grouting/guiniting and micro concreting depending on type of defect noticed 30 days IRC SP: 40-2019 and MORTH specification 2800
Bridges including Flyover and Viaducts etc. - Bridge Substructure Delamination of reinforcement not more than 5%, cracking or tearing of rubber not more than 2 locations per side, no rupture of reinforcement or rubber Bi-Annually Detailed condition survey as per IRC SP: 35-1990 using Mobile Bridge Inspection unit. In case of failure of even one bearing on any pier/abutment, all the bearings on that pier/abutment shall be replaced, in order to get uniform load transfer on to bearings. 3 months MORTH specification 2810, IRC SP: 40-2019 and IRC:83 (Part-II)-2018
POT/PFFE and Spherical Bearings No locking of movable and rotational parts, No Corrosion, Cleanliness Bi-Annually Detailed condition survey as per IRC SP: 35-1990 using Mobile Bridge Inspection unit. Unlocking of affected parts, Cleaning of Rust and repainting. General Cleaning of bearings. 30 days IRC:83 (Part-III)-2018, IRC:83 (Part-IV)-2014
Scouring around Foundations Scouring shall not be lower than maximum scour level for the bridge Bi-Annually Condition survey and visual inspection as per IRC SP:35-1990 using Mobile Bridge Inspection Unit. In case of doubt Underwater camera for Inspection of deep wells in Major Rivers. Suitable protection works around pier/abutment 1 month IRC SP: 40-2019, IRC: 89-2019, IRC:78-2014, MORTH specification 2500
Protection works in good condition Damaged of rough stone apron or bank revetment not more than 3 sq.m, damage to solid apron (concrete apron) not more than 1 sq.m 2 times in a year (before and after rainy season) Condition survey as per IRC SP:35-1990 Repairs to damaged aprons and pitching 30 days after Defect observation or 2 weeks before onset of rainy Season whichever is earlier. IRC: SP 40-2019, IRC: SP:13- 2004 and IRC:89-2019