National Highways Authority of India
Table 1: Maintenance Criteria for Pavements
Asset Type | Performance Parameter | Desirable | Acceptable | Frequency of Inspection | Tools/Equipment | Standards and References for Inspection and Data Analysis | Time limit for Rectification / Repair | Maintenance specifications |
---|---|---|---|---|---|---|---|---|
Flexible Pavement Routine Inspection (Pavement of MCW, Service Road, Approach of Grade structures, approaches of connecting roads, slip roads, lay byes etc. as applicable) | Potholes | Nil | <0.1% of area and subjected to limit of 10mm in depth | Daily | Length Measurement Unit like Scale, Tape, odometer etc. | MORT&H | 24-48 hours | MORT&H Specification 3004.2 |
Cracking | Nil | <5% subject to limit of 0.5 sqm for any 50m length | Daily | 7-15 days | MORT&H Specification 3004.3 | |||
Rutting | Nil | <5mm | Daily | Straight Edge | IRC 82: 2015 and | 15-30 days | MORT&H Specification 3004.2 | |
Corrugations and Shoving | Nil | 0.1% of area | Daily | Length Measurement | Distress Identification Manual for Long Term Pavement Performance Program, FHWA 2003 | 2-7 days | IRC:82-2015 | |
Bleeding | Nil | <1% of area | Daily | Unit like Scale, Tape, odometer etc. | 3-7 days | MORT&H Specification 3004.4 | ||
Ravelling/ Stripping | Nil | <1% of area | Daily | Length Measurement Unit like Scale, Tape, odometer etc. | 7-15 days | IRC:82-2015 read with IRC SP-81 | ||
Edge Deformation / Breaking | Nil | and/or width <0.1m at any Location restricted to 30cm from the edge. <1m for any 100m section | Daily | 7-15 days | IRC:82-2015 | |||
Roughness | 2000 mm/km | 2400 mm/km | Bi-Annually | Network Survey vehicle (NSV) with all its module such as Laser Profilometers, Transverse profile logger, Laser crack measurement system, Video logging modules, high resolution Odometer etc. | ASTM E950 (98) :2004 Standard Test Method for measuring Longitudinal Profile of Travelled Surfaces with Accelerometer Established Inertial Profiling Reference and ASTM E1656 -94:2000- Standard Guide for Classification of Automatic Pavement Condition Survey Equipment | 180 days | IRC:82-2015 | |
Rutting | <10mm for any 50 m section and/or, length of section <5m | <10mm for any 50 m section and/or, length of section <10m | Bi-Annually | 15-30 days | IRC:82-2015 | |||
Pavement rating based on distress per IRC 82 / Pavement Condition Index as per ASTM 6433-07 | >3/85 | >2.1/70 | Bi-Annually | 180 days | IRC:82-2015/ ASTM D 6433-07 | |||
Flexible Pavement Programmed Inspection | Other Pavement Distresses | - | - | Bi-Annually | 2-7 days | IRC:82-2015 | ||
Skid | 60SN | 50SN | Bi-Annually | SCRIM (Sideway force Coefficient Routine Investigation Machine or equivalent) British Pendulum Tester | BS:7941-1:2006, IRC:82-2015/ ASTM 274 | 180 days | IRC:82-2015 | |
Deflection/ Remaining Life | - | Annually | Falling Weight Deflectometer | IRC 115: 2014 | 180 days | IRC:115-2014 | ||
Rigid Pavement (Pavement of MCW, Service Road, Grade separated structure, approaches of connecting roads, slip roads, lay byes etc. as applicable. | Roughness BI | <2200mm/km | <2400mm/km | Bi-Annually | Class I Profilometer Mounted on NSV | ASTM E950 (98) :2004 and ASTM E1656 -94: 2000 | 180 days | IRC: SP:83-2018 |
Skid | Skid Resistance No. at different speed of vehicles Minimum SN Traffic Speed 36 50 33 65 32 80 31 95 31 100 | Bi-Annually | SCRIM (Sideway force Coefficient Routine Investigation Machine or equivalent) British Pendulum Tester | 180 days | IRC: SP:83-2018 | |||
Embankment /Slope | Edge drops at shoulders | Nil | 40mm | Daily | Length Measurement Unit like Scale, Tape, odometer etc. | IRC | 7-15 days | MORT&H Specification |
Slope of camber/cross fall | Nil | <2% variation in prescribed slope of camber /cross fall | Daily | 7-15 days | MORT&H Specification | |||
Embankment Slopes | Nil | <15 % variation in prescribe side slope | Daily | 7-15 days | MORT&H Specification | |||
Embankment Protection | Nil | Nil | Daily | NA | 7-15 days | MORT&H Specification | ||
Rain Cuts/Gullies in slope | Nil | Nil | Daily Specially During Rainy Season | NA | IRC | 7-15 days | MORT&H Specification | |
Cut Section/ Slope | Unstable Slopes | Nil | - | NA | IRC | 2-7 days | MORT&H Specification |
Table 2: Maintenance Criteria for Rigid Pavements
S. No | Type of Distress | Measured Parameter | Degree of Severity | Assessment Rating | Repair Action | ||
---|---|---|---|---|---|---|---|
For the case d < D/2 | For the case d > D/2 | ||||||
CRACKING | 1 | Single Discrete Cracks Not intersecting with any joint or Single Transverse (or Diagonal) Crack intersecting with one or more joints | w = width of crack, L = length of crack, d = depth of crack, D = depth of slab | 0 | Nil, not discernible | No Action | - |
1 | w < 0.2 mm. hair cracks | Seal without delay | Full Depth Repair Dismantle and reconstruct affected portion - See Para 5.4, within 15 days | ||||
2 | w = 0.2 - 0.5 mm, discernible from slow-moving car | ||||||
3 | w = 0.5 - 1.5 mm, discernible from fast-moving car | Seal and stitch if L > l m. within 7 days | |||||
4 | w = 1.5 - 3.0 mm | ||||||
5 | w > 3 mm. | ||||||
2 | Single Transverse (or Diagonal) Crack intersecting with one or more joints | w = width of crack L = length of crack d = depth of crack D = depth of slab | 0 | Nil, not discernible | No Action | ||
1 | w < 0.2 mm. hair cracks | Route and seal with Epoxy within 7 days | Seal Staple within 15days & Cross stich or | ||||
2 | w = 0.2 - 0.5 mm, discernible from slow-moving car | ||||||
3 | w = 0.5 3.0 mm, discernible from fast-moving car | Seal and stitch, if L > l m. within 7 days | Full Depth Repair Dismantle and reconstruct affected portion with norms & Specifications - See Para 5.5 &refer chapter 9 of IRC: SP: 83-2018, within 15 days. | ||||
4 | w = 3.0 - 6.0 mm | Not Applicable | Staple or Dowel Bar Retrofit within 15 days. | ||||
5 | w > 6 mm, usually associated with spalling, and/or slab rocking under traffic | Not Applicable, (full depth crack) | Staple or Dowel Bar Retrofit within 15 days | ||||
3 | Single Longitudinal Crack intersecting with one or more joints | w = width of crack L = length of crack d = depth of crack D = depth of slab | 0 | Nil, not discernible | No Action | ||
1 | w < 0.5 mm, discernable from slow moving vehicle | Seal and stich if L >l m within 7 days | Seal and Cross-Stich or Staple within 15 days | ||||
2 | w = 0.5 - 3.0 mm, discernible from fast vehicle | Seal & Staple, within 15 days | Partial Depth Repair with or without dowel bar retrofit within 15 days or | ||||
3 | w = 3.0 - 6.0 mm | ||||||
4 | w = 6.0 - 12.0 mm, usually associated with spalling | Not applicable | |||||
5 | w > 12 mm, usually associated with spalling, and/or slab rocking under traffic | Not Applicable, (Rocking/ Spalling indicates full depth crack) | Full Depth Repair Dismantle and reconstruct affected portion - See Fig 5.6 and Chapter 9 of IRC: SP:83-2018, within 15 days | ||||
4 | Multiple Cracks intersecting with one or more joints | w = width of crack | 0 | Nil, not discernible | No Action | ||
1 | w < 0.2 mm. hair cracks | Seal and stitch if L > l m. within 15 days | Dismantle and Reconstruct whole slab as per Specifications within 30days. | ||||
2 | w = 0.2 - 0.5 mm, discernible from slow-moving car | ||||||
3 | w = 0.5 3.0 mm, discernible from fast-moving car | Full depth repair within 15 days | |||||
4 | w = 3.0 - 6.0 mm panel broken into 2 or 3 pieces | Reinstate sub- base, reconstruct whole slab within 30days. | |||||
5 | w > 6 mm and/or panel broken into more than 4 pieces | ||||||
5 | Corner Break | w = width of crack, L = length of crack | 0 | Nil, not discernible | No Action | ||
1 | w < 0.5 mm; only 1 corner broken | Seal with low viscosity epoxy to secure broken parts within 7 days | |||||
2 | w < 1.5 mm; L < 0.6 m, only one corner broken | Partial Depth (Refer Figure 8.3 of IRC: SP:83-2018) within 15 days | |||||
3 | w < 1.5 mm; L < 0.6 m, two corners broken | ||||||
4 | w > 1.5 mm; L > 0.6 m or three corners broken | Full depth repair within 30 days. | |||||
5 | three or four corners broken | Reinstate sub-base, and reconstruct the slab as per norms & Specifications within 30 days. | |||||
6 | Punchout (Applicable to Continuous Reinforced Concrete Pavement CRCP only) | w = width of crack L = length (m/m2) | 0 | Nil, not discernible | No Action | Not Applicable, (Punch-out is full depth Distress) | |
1 | w < 0.5 mm; L < 3 m/m2 | Full depth repair - Cut out and replace damaged area taking care not to damage reinforcement. Within 30 days. | Seal with low viscosity epoxy to secure broken parts Within 15 days | ||||
2 | either w > 0.5 mm or L < 3 m/m2 | ||||||
3 | w > 1.5 mm and L < 3 m/m2 | ||||||
4 | w > 3 mm, L < 3 m/m2 and deformation | ||||||
5 | w > 3 mm, L > 3 m/m2 and deformation | ||||||
Surface Defects | 7 | Ravelling or Honeycomb type surface | r = area damaged surface/total surface of slab (%) h = maximum depth of damage | 0 | Nil, not discernible | No action. | Not Applicable |
1 | r < 2 % | Local repair of areas damaged and liable to damage. Within 15 days | |||||
2 | r = 2 - 10 % | ||||||
3 | r = 10-25% | Bonded Inlay, if affecting 2 or 3 slabs. Within 30 days | |||||
4 | r = 25 - 50 % | ||||||
5 | r > 50% and h > 25 mm | Reconstruct slabs, if affecting 4 or more slabs. Within 30 days | |||||
8 | Scaling | r = area damaged surface/total surface of slab (%) h = maximum depth of damage | 0 | Nil, not discernible | No action. | Not Applicable | |
1 | r < 2 % | Local repair of areas damaged and liable to within 7 days | |||||
2 | r = 2 - 10 % | Bonded Inlay within 15 days | |||||
3 | r = 10 - 20% | ||||||
4 | r = 20 - 30 % | ||||||
5 | r > 30 % and h > 25 mm | Reconstruct slab within 30 days. | |||||
9 | Polished Surface/Glazing | t = texture depth, sand patch test | 0 | No action. | Not Applicable | ||
1 | t > 1 mm | Monitor rate of deterioration | |||||
2 | t = 1 - 0.6 mm | ||||||
3 | t = 0.6 - 0.3 mm | ||||||
4 | |||||||
5 | t < 0.3 mm | Diamond Grinding if affecting 50% or more slabs in a continuous stretch of minimum 5 km. Within 30 days | |||||
10 | Popout (Small Hole), Pothole Refer Para 8.4 | n = number/m2, d = diameter, h = maximum depth | 0 | d < 50 mm; h < 25 mm; n < 1 per 5 m2 | No action. | Not Applicable | |
1 | d = 50 - 100 mm; h < 50 mm; n < 1 per 5 m2 | Partial depth repair 65 mm deep. Within 15 days | |||||
2 | d = 50 - 100 mm; h > 50 mm; n < 1 per 5 m2 | ||||||
3 | d = 100 - 300 mm; h < 100 mm n < 1 per 5 m2 | Partial depth repair 110mm i.e.,10 mm more than the depth of the hole within 30 days | |||||
4 | d = 100 - 300 mm; h > 100 mm; n < 1 per 5 m2 | ||||||
5 | d > 300 mm; h > 100 mm: n > 1 per 5 m2 | Full depth repair within 30 days. | |||||
JOINT DEFECT | 11 | Joint Seal Defects | loss or damage L = Length as % total joint length | 0 | Difficult to discern. | No action. | |
1 | Discernible, L< 25% but of little immediate consequence with regard to ingress of water or trapping incompressible material. | Clean joint, inspect later. | Not Applicable | ||||
3 | Notable. L > 25% insufficient protection against ingress of water and trapping | Clean and reapply sealant in selected locations. Within 7 days. | Not Applicable | ||||
5 | Severe; w > 3 mm negligible protection against ingress of water and trapping incompressible material. | Clean, widen and reseal the joint following strict procedures within 7 days. | |||||
12 | Spalling of Joints | w = width on either side of the joint L = length of spalled portion (as % joint length) | 0 | Nil, not discernible | No action. | ||
1 | w < 10 mm | Apply low viscosity epoxy resin/mortar in cracked portion within 7 days | |||||
2 | w = 10 - 20 mm, L < 25% | ||||||
3 | w = 20 - 40 mm, L > 25% | Partial Depth Repair, 30 - 50 mm deep, h = w+ 20% of w, within 30 days | |||||
4 | w = 40 - 80 mm, L > 25% | ||||||
5 | w > 80 mm, and L > 25% | 50 - 100 mm deep repair. H = w + 20% of w, within 30 days | |||||
13 | Faulting (or Stepping) in Cracks or Joints | f = difference of level | 0 | not discernible, < 1 mm | No action. | ||
1 | f < 3 mm | ||||||
2 | f = 3 - 6 mm | Determine cause and observe | |||||
3 | f = 6 - 12 mm | Diamond Grinding within 15 days | |||||
4 | f= 12 - 18 mm | Raise sunken slab within 15 days. | |||||
5 | f> 18 mm | Strengthen subgrade and sub-base by grouting, within 30 days. | |||||
14 | Blowup or Buckling | h = vertical displacement from normal profile | 0 | Nil, not discernible | No action. | ||
1 | h < 6 mm | Install Signs to Warn Traffic, within 24 hours days | |||||
2 | h = 6 - 12 mm | ||||||
3 | h = 12 - 25 mm | ||||||
4 | h > 25 mm | Full Depth Repair, within 30 days. | |||||
5 | shattered slabs, i.e. 4 or more pieces | Replace broken slabs, within 30 days. | |||||
15 | Depression | h = negative vertical displacement from normal profile. L = length | 0 | Not discernible. h < 5 mm | No action. | ||
1 | h = 5 - 15 mm | Install Signs to Warn Traffic, within 24 hours | |||||
2 | h = 15 - 30 mm, Nos<20% joints | ||||||
3 | h = 30 - 50 mm | ||||||
4 | h > 50 mm or > 20% joints | Strengthen subgrade. Reinstate pavement at normal level, within 30 days. | |||||
5 | h > 100 mm | ||||||
16 | Heave | h = positive vertical displacement from normal profile. L = length | 0 | Not discernible. h < 5 mm | No action. | ||
1 | h = 5 - 15 mm | Follow up. | |||||
2 | h = 15 - 30 mm, Nos<20% joints | Install Signs to Warn Traffic, within 24 hours | |||||
3 | h = 30 - 50 mm | ||||||
4 | h > 50 mm or > 20% joints | Stabilise subgrade. Reinstate pavement at normal level, within 30 days | |||||
5 | h > 100 mm | ||||||
17 | Bump | h = vertical displacement from normal profile | 0 | No action. | |||
1 | h = 4 - 7 mm | Grind, in case of new construction. Within 7 days | |||||
3 | h = 7 - 15 mm | Grind in case of Ongoing maintenance within 15 days | |||||
5 | h > 15 mm | ||||||
18 | Lane to Shoulder Drop- off | f = difference of level | 0 | not discernible < 3mm | No action. | ||
1 | f = 3 - 10 mm | Spot repair of shoulder. Within 3 days | |||||
2 | f = 10 - 25 mm | ||||||
3 | f = 25 - 50 mm | Fill up shoulder within 7 days | |||||
4 | f = 50 - 75 mm | For any 100 m segment, Reconstruct shoulder, if affecting 25% or more of segment, within 30 days. | |||||
5 | f > 75 mm | ||||||
DRAINAGE | 19 | Pumping | quantity of fines and water expelled through open joints and cracks Nos/100 m stretch | 0 | not discernible | No action. | |
1 to 2 | slight/occasional Nos< 10% | Repair cracks and joints without delay | Inspect and repair Sub-drainage at distressed sections and upstream | ||||
3 to 4 | appreciable/Frequent 10 - 25% | Lift or jack slab within 30 days. | |||||
5 | abundant, crack development > 25% | Repair distressed pavement sections. Strengthen subgrade And sub-base. Replace slab. Within 30 days. | |||||
20 | Ponding | Ponding on slabs due to blockage of drains | 0-2 | No discernible problem | No action. | Action required to stop water damaging foundation within 15 days. | |
3 to 4 | Blockages observed in drains, but water flowing | Clean drains etc., follow up, deep groving in transverse direction to remove | |||||
5 | Ponding, accumulation of water observed | Deep groving in transverse direction to remove water-hydro planning within 7 days |
Table 3: Maintenance Criteria for Safety Related Items and Other Furniture Items
Asset Type | Performance Parameter | Level of Service (LOS) | Design Speed (kmph) | Desirable Minimum Sight Distance (m) | Safe Stopping Sight Distance (m) | Frequency of Measurement | Testing Method | Recommended Remedial Measures | Time limit for Rectification | Specifications and Standards |
---|---|---|---|---|---|---|---|---|---|---|
Highway | Availability of Safe Sight Distance | As per IRC SP:84-2019, a minimum of safe stopping sight distance shall be available throughout. | 100 | 360 | 180 | Monthly | Manual Measurements With Odometer along with video/ image backup | Removal of obstruction within 24 hours, in case of sight line affected by temporary objects such as trees, temporary encroachments. In case of permanent structure or design deficiency: * Removal of obstruction/ improvement of deficiency at the earliest * Speed Restriction boards and suitable traffic calming measures such as transverse bar marking, blinkers, etc. shall be applied during the period of rectification. | IRC: SP:84-2019 | |
80 | 260 | 130 | ||||||||
Pavement Marking Wear | <70% of marking remaining | Bi-Annually | Visual Assessment as per Annexure- F of IRC:35-2015 | Re-Painting Cat-1 Defect within 24 hours Cat-2 Defect within 2 months | IRC:35-2015 | |||||
Day time Visibility | During expected life Service Time - 130mcd/m2/lux - 100mcd/m2/lux | Monthly | As per Annexure- D of IRC:35- 2015 | Re-Painting Cat-1 Defect within 24 hours Cat-2 Defect within 2 months | IRC:35-2015 | |||||
Night Time Visibility | Initial and Minimum Performance for Dry Retro reflectivity during night time: | Design Speed (RL) Retro-Reflectivity (mcd/m²/lux) | Initial (7Days) | Minimum Threshold Level and warranty period required up to 2 years (TL) | Bi-Annually | As per Annexure-E of IRC:35- 2015 | Re-Painting Cat-1 Defect within 24 hours Cat-2 Defect within 2 months | IRC:35-2015 | ||
Up to 65 | 200 | 80 | ||||||||
65 - 100 | 250 | 120 | ||||||||
above 100 | 350 | 150 | ||||||||
Initial and Minimum Performance for Night Visibility under wet condition (Retro reflectivity): | mcd/m2/lux | mcd/m2/lux | ||||||||
Skid Resistance | Initial and Minimum performance for Skid Resistance *Note: shall be considered under urban/city traffic condition encompassing the locations like pedestrian crossings, bus bay, bus stop, cycle track intersection delineation, transverse bar markings etc. | Bi-Annually | As per Annexure-G of IRC:35- 2015 | Within 24 hours | IRC:35-2015 | |||||
Road Sign | Shape and Position | Shape and Position as per IRC:67- 2012. Signboard should be clearly visible for the design speed of the section | Daily | Visual with video/image backup | Improvement of shape, in case if shape is damaged. Relocation as pe requirement | 48 hours in case of Mandatory Signs, Cautionary and Informatory Signs (Single and Dual post signs), 15 Days in case of Gantry/ Cantilever Sign boards | IRC:67-2012 | |||
Retro reflectivity | As per specifications in IRC:67-2012 | Bi-Annually | Testing of each signboard using Retro Reflectivity Measuring Device. In accordance with ASTM D 4956-09 | Change of signboard | 48 hours in case of Mandatory Signs, Cautionary and Informatory Signs (Single and Dual post signs). 1 Month in case of Gantry/ Cantilever Sign boards | IRC:67-2012 | ||||
Kerb | Kerb Height | As per IRC 86:2018 depending upon type of Kerb | Bi-Annually | Use of distance measuring tape | Raising Kerb Height | Within 1 Month | IRC 86:2018 | |||
Kerb Painting Functionality | Functioning of Kerb painting as intended | Daily | Visual with video/image backup | Kerb Repainting | Within 7-days | IRC 35:2015 | ||||
Other Road Furniture | Reflective Pavement Markers (Road Studs) | Numbers and Functionality as per specifications in IRC: SP:84-2019 and IRC:35-2015, unless specified in Schedule-B. | Daily | Counting | New Installation | Within 2 months | IRC: SP:84-2019, IRC:35-2015 | |||
Pedestrian Guardrail Functionality | Functioning of guardrail as intended | Daily | Visual with video/image backup | Rectification | Within 15 days | IRC: SP:84-2019 | ||||
Traffic Safety Barriers Functionality | Functioning of Safety Barriers as intended | Daily | Visual with video/image backup | Rectification | Within 7-days | IRC: SP:84-2019, IRC:119-2015 | ||||
End Treatment of Traffic Safety Barriers Functionality | Functioning of End treatment as intended | Daily | Visual with video/image backup | Rectification | Within 7-days | IRC: SP:84-2019, IRC:119-2015 | ||||
Attenuators Functionality | Functioning of Attenuators as intended | Daily | Visual with video/image backup | Rectification | Within 7-days | IRC: SP:84-2019, IRC:119-2015 | ||||
Guard Posts and Delineators Functionality | Functioning of Guard Posts and Delineators as intended | Daily | Visual with video/image backup | Rectification | Within 15 days | IRC:79-2019 | ||||
Overhead Sign Structure | Overhead sign structure shall be structurally adequate | Daily | Visual with video/image backup | Rectification | Within 15 days | IRC:67-2012 | ||||
Traffic Blinkers Functionality | Functioning of Traffic Blinkers as intended | Daily | Visual with video/image backup | Rectification | Within 7-days days | IRC: SP:84-2019 | ||||
Highway Lighting System Highway Lights | Illumination: Minimum 40 Lux illumination on the road surface | Daily | The illumination level shall be measured with lux- meter | Improvement in Lighting System | 24 hours | IRC: SP:84-2019 | ||||
No major failure in the lighting system | Daily | - | Rectification of failure | 24 hours | IRC: SP:84-2019 | |||||
No minor failure in the lighting system | Monthly | - | Rectification of failure | IRC: SP:84-2019 | ||||||
Toll Plaza Canopy Lights Minimum 40 Lux illumination on the road surface | Daily | The illumination level shall be measured with lux- meter | Improvement in Lighting System | 24 hours | IRC: SP:84-2019 | |||||
No major/minor failure in the lighting system | Daily | Rectification of failure | 8 hours | IRC: SP:84-2019 | ||||||
Trees and plantation including median plantation | Obstruction in a minimum head- room of 5.5 m above carriageway or obstruction in visibility of road signs | Monthly | Visual with video/image backup | Removal of trees | Immediate | IRC: SP:84-2019 | ||||
Deterioration in health of trees and bushes | Daily | Visual with video/image backup | Timely watering and treatment. Or Replacement of Trees and Bushes. | Within 90 days | IRC: SP:84-2019 | |||||
Vegetation affecting sight line and road structures | Daily | Visual with video/image backup | Removal of trees | Immediate | IRC: SP:84-2019 | |||||
Rest Area Cleaning of toilets | Daily | - | - | Every 4 hours | - | |||||
Defects in electrical, water and sanitary installations | Daily | - | Rectification | 24 hours | - | |||||
Other Project Facilities and Approach roads | Damage or deterioration in Approach Roads, pedestrian facilities, truck lay-bys, bus-bays, bus-shelters, cattle crossings, Traffic Aid Posts, Medical Aid Posts, and other works | Daily | - | Rectification | 15 Day | IRC: SP:84-2019 |
Table 4: Maintenance Criteria for Structures and Culverts
Asset Type | Performance Parameter | Level of Service (LOS) | Frequency of Measurement | Testing Method | Recommended Remedial measures | Time limit for Rectification | Specifications and Standards |
---|---|---|---|---|---|---|---|
Pipe/box/slab culverts | Free waterway/ unobstructed flow section | 85% of culvert normal flow area to available. | 2 times in a year (before and after rainy season) | Inspection by Bridge Engineer as per IRC SP: 35- 1990 and recording of depth of silting and area of vegetation | Cleaning silt up soils and debris in culvert barrel after rainy season, removal of bushes and vegetation, U/s of barrel, under barrel and D/s of barrel before rainy season. | 15 days before onset of monsoon and within 30 days after end of rainy season. | IRC 5-2015, IRC SP:40-2019 and IRC SP:13-2004 |
Leak-proof expansion joints if any | No leakage through expansion joints | Bi-Annually | Physical inspection of expansion joints as per IRC SP: 35- 1990 if any, for leakage strains on walls at joints. | Fixing with sealant suitably | 30 days or before onset of rains whichever comes earlier | IRC SP:40-2019 and IRC SP:69-2011 | |
Structurally sound | Spalling of concrete not more than 0.25 sq.m. | Bi-Annually | Detailed inspection of all components of culvert as per IRC SP:35-1990 and recording the defects | Repairs to spalling, cracking, delamination, rusting shall be followed as per IRC: SP:40-2019. | 15 days | IRC SP 40-2019 and MORTH Specifications clause 2800 | |
Delamination of concrete not more than 0.25 sq.m. | |||||||
Cracks wider than 0.3 mm not more than 1m aggregate length | |||||||
Protection works in good condition | Damaged of rough stone apron or bank revetment not more than 3 sq.m, damage to solid apron (concrete apron) not more than 1 sq.m | 2 times in a year (before and after rainy season) | Condition survey as per IRC SP:35-1990 | Repairs to damaged aprons and pitching | 30 days after defect observation or 2 weeks before onset of rainy season whichever is earlier. | IRC: SP 40-2019 and IRC SP:13-2004 | |
Bridges including Flyover and Viaducts etc. as applicable | Riding quality | No pothole in wearing coat on bridge deck | Daily | Visual inspection as per IRC SP:35-1990 | Repairs to BC or wearing coat | 15 days | MORT&H Specification 2811 |
Bumps | No bump at expansion joint | Daily | Visual inspection as per IRC SP:35-1990 | Repairs to BC on either side of expansion joints, profile correction course on approach slab in case of settlement to approach embankment | 15 days | MORT&H Specification 3004.2 & 2811 | |
Bridges including Flyover and Viaducts etc. -Super Structure | User safety (condition of crash barrier and guard rail) | No damaged or missing stretch of crash barrier or pedestrian hand railing | Daily | Visual inspection and detailed condition survey as per IRC SP: 35-1990 | Repairs and replacement of safety barriers as the case may be | 3days | IRC: 5-2015, IRC SP: 84-2019 and IRC SP: 40- 2019 |
Rusted reinforcement | Not more than 0.25 sq.m | Bi-Annually | Detailed condition survey as per IRC SP: 35-1990 using Mobile Bridge Inspection unit. | Repairs to spalling, cracking, delamination, rusting shall be followed as per IRC: SP:40-2019. | 15 days | IRC SP: 40-2019 and MORTH Specification 2800 | |
Spalling of concrete | Not more than 0.50 sq.m | ||||||
Delamination | Not more than 0.50 sq.m | ||||||
Cracks wider than 0.30 mm | Not more than 1m total length | ||||||
Rainwater seepage through deck slab | Leakage - nil | ||||||
Deflection due to permanent loads and live loads | Within design limits. | Once in every 10 years for spans more than 40 m | Load test method | Carry out major rehabilitation works on bridge to retain original design loads | 6 months | IRC SP: 51-2015 | |
Vibrations in bridge deck due to moving trucks | Frequency of vibrations shall not be more than 5 Hz | Once in every 5 years for spans more than 30m and every 10 years for spans between 15 to 30 | Laser displacement sensors or laser vibro- meters | Strengthening of super structure | 4 months | AASHTO, LRFD specifications | |
Bridges including Flyover and Viaducts etc. -Super Structure | Leakage in Expansion joints | No damage to elastomeric sealant | Bi-Annually | Detailed condition survey as per IRC SP: 35-1990. using Mobile Bridge Inspection Unit. | Replacement of seal in expansion joint. Replacement of Sealing compound in case of leakage I case of copper strip type joint. | 15 days | MORTH specifications 2600, IRC SP: 40- 2019. |
Debris and dust in strip seal expansion joint | No dust or debris in expansion joint gap. | Monthly | Detailed condition survey as per IRC SP: 35-1990. using Mobile Bridge Inspection Unit. | Cleaning of expansion joint gaps thoroughly | 3 days | MORTH specifications 2600, IRC SP: 40-2019 and IRC: SP:69-2011 | |
Drainage spouts | No down take Pipe missing/broken below soffit of the deck slab. No silt, debris, clogging of drainage spout collection chamber. | Monthly | Detailed condition survey as per IRC SP: 35-1990. using Mobile Bridge Inspection Unit. | Cleaning of drainage spouts thoroughly. Replacement of missing/broken down take pipes with a minimum pipe extension of 500mm below soffit of slab. Providing sealant around the drainage spout if any leakages observed. | 3 days | MORTH specification 2700 | |
Cracks/ spalling of concrete /rusted steel | No cracks, spalling of concrete and rusted steel | Bi-Annually | Detailed condition survey as per IRC SP:35-1990 using Mobile Bridge Inspection Unit. | All the corroded reinforcement shall need to be thoroughly cleaned from rusting and applied with anti- corrosive coating before carrying out repairs to substructure by grouting/guiniting and micro concreting depending on type of defect noticed | 30 days | IRC SP: 40-2019 and MORTH specification 2800 | |
Bridges including Flyover and Viaducts etc. - Bridge Substructure | Delamination of reinforcement not more than 5%, cracking or tearing of rubber not more than 2 locations per side, no rupture of reinforcement or rubber | Bi-Annually | Detailed condition survey as per IRC SP: 35-1990 using Mobile Bridge Inspection unit. | In case of failure of even one bearing on any pier/abutment, all the bearings on that pier/abutment shall be replaced, in order to get uniform load transfer on to bearings. | 3 months | MORTH specification 2810, IRC SP: 40-2019 and IRC:83 (Part-II)-2018 | |
POT/PFFE and Spherical Bearings | No locking of movable and rotational parts, No Corrosion, Cleanliness | Bi-Annually | Detailed condition survey as per IRC SP: 35-1990 using Mobile Bridge Inspection unit. | Unlocking of affected parts, Cleaning of Rust and repainting. General Cleaning of bearings. | 30 days | IRC:83 (Part-III)-2018, IRC:83 (Part-IV)-2014 | |
Scouring around Foundations | Scouring shall not be lower than maximum scour level for the bridge | Bi-Annually | Condition survey and visual inspection as per IRC SP:35-1990 using Mobile Bridge Inspection Unit. In case of doubt Underwater camera for Inspection of deep wells in Major Rivers. | Suitable protection works around pier/abutment | 1 month | IRC SP: 40-2019, IRC: 89-2019, IRC:78-2014, MORTH specification 2500 | |
Protection works in good condition | Damaged of rough stone apron or bank revetment not more than 3 sq.m, damage to solid apron (concrete apron) not more than 1 sq.m | 2 times in a year (before and after rainy season) | Condition survey as per IRC SP:35-1990 | Repairs to damaged aprons and pitching | 30 days after Defect observation or 2 weeks before onset of rainy Season whichever is earlier. | IRC: SP 40-2019, IRC: SP:13- 2004 and IRC:89-2019 |