Tender Penalty Calculations For Delay in Work
Generally, in Government organizations Penalty clause is included in
Tender stating that, if at any stage of work, it is found that the execution of
work is not as per the planning (As mentioned in Programme & Progress
Schedule) a fine shall be imposed on the contractor as mentioned in clause
No.xxxxx of conditions of contract.
Compensation amount is
generally equal to one percent or such smaller amount as Superintendent Engineer (whose
decision in writing shall be final) may decide of the said estimated cost of
the whole work for everyday that the due quantity of work remains incomplete provided
always that the total amount of compensation to be paid under the provisions of
this clause shall not exceed 10% of the estimated cost of the work as shown in
the tender. Chief Engineer should be the final authority
If there is delay in completion
of work, as per work completion period in Tender according to conditions Then
Starting Penalty Amount = a
Increment in Penalty = d
Penalty Period = n
Then Total Penalty (C) can be calculated as
$$C = {{n\over 2} \times\left[2a+(n-1) d\right]} ............................(1) $$
Now if the condition for
Compensation is that total amount of compensation to be paid under the
provisions of this clause shall not exceed 10% of the estimated cost of the
work.
if ' A ' is Total estimated
amount of Work then
compensation C < = 10% A
Therefore,
$${\text{10 % A}} ={n\over2} \times {\left [2 a + ( n - 1) d \right]} ................(2) $$
Now
The work Executed in Phases,
let's assume 4 phases of time period T as below
¼ of the work in ¼T of the
time.
½ of the work in ½T of the
time.
¾ of the work in ¾T of the
time.
Full work in T
time............................ months including monsoon.
so, each phase have its own
estimated cost
AT = A¼T +
A(½T - ¼T ) + A(¾T - ½T) + A(T - ¾T)
Hence,
10% AT = 10% {A¼T
+ A(½T - ¼T ) + A(¾T - ½T) + A(T -
¾T)}
So, penalty for Phase I, if t1 days remaining for completion of phase I for starting amount a1
10% {A¼T } = (t1) /2 [2a1 + (t1-1)d]
So, penalty for Phase II, if t2 days remaining for completion of phase II for starting amount a2
10%
{ A(½T - ¼T ) } = (t2) /2 [2a2 + (t2-1)d]
So, penalty for Phase III, if t3 days remaining for completion of phase III for starting amount a3
10%
{ A(¾T - ½T) } = (t3) /2 [2a3 + (t3-1)d]
So, penalty for Phase IV, if t4 days remaining for completion of phase IV for starting amount a4
10% { A(T - ¾T)} = (t4) /2 [2a4 + (t4-1)d]
Note:- for constant Value of Penalty difference 'd' can be kept 0.Any corrections or Suggestions will be appreciated.
5 Comments
Good info saheb
ReplyDeleteI just tried to put it in mathematical form after reading tender document
DeleteSir,
ReplyDeleteCan we make a excel sheet for above calculation?
Excel sheet for above calculations is possible
ReplyDeleteCalculations are embedded in page itself
ReplyDeleteIf you have any doubts, suggestions , corrections etc. let me know