GEOTECHNICAL SPECIAL INSPECTIONS
"" "" ""Materials | Test to be conducted | Ref. IS Codes | Frequency of Inspection / Testing |
Soil | Sand Replacement Method (including calibration of rapid moisture metre) | IS 2720 , specification | At every 100 m2 of compacted area for small plinth filling |
Choice /suitability of soil LL,PL, Shrinkage limit, grain size analysis | At every 500 m3. of compacted earth filling for mass filling work or a day work. which ever is minimum | ||
Once for one borrow area as marked by contractor and as instructed by client’s representative | |||
Proctor Test (Heavy compaction) | Once for each source of earth or as required by engineer | ||
Fine Aggregates | Total Deleterious materials content (Clay lumps, Coal, Lignite, Soft particles or impurities) | IS 2386 part-II | Once per source . |
Water absorption (if >2% found,soundness test is required) | IS 2386 part-II | Once per Month . | |
Sp. Gravity | IS 2386 part-II | Once per month . | |
Silt and clay content | IS 2386 part-II | Every day for first 7 days and later once in every week. | |
Particle size distribution | IS 2386 part-I andIS 383 | Twice in a week (DAILY) | |
Moisture Content | IS 2386 part III and IS 383 | Once in day except during monsoon when it has to be done at least twice a day / during the work (Subjected to producing Structural Conc.at site) | |
Coarse Aggregates | Particle size distribution | IS 2386 part-I 383 | One test daily for first 7 days recd. Of materials , latter twice for every week but insp. through only 20MM/ 10MM sieve for every 5 truck received qty. at site . |
Percentage of soft deleterious material | IS 2386 Part- II | Once per source . | |
Moisture Content | IS 2386 part- III IS 383 | Once in day except, during monsoon,for every load | |
Flakiness Index | IS2386 Part-I | Once in every Week. | |
Elongation Index | IS 2386 Part-I | Once in every Week. | |
Mechanical Properties | IS 2386 part-IV | Twice per Month . | |
Agg. Crushing value | |||
Impact Value | |||
Chloride and sulphate content | IS-456 | Once per source . | |
Water absorption (if >2% found,soundness test is required) | IS 2386 part-II | Once per month . | |
Sp. Gravity | IS 2386 Part-III | Once per month . | |
Petro graphic Analysis | IS 2386 Part-VIII | Once per source . | |
Alkali Aggregate reaction | IS 2386 part-VII | Once per source . | |
Water | Chemical and Physical properties | IS- 3025 | From each source before start of work . |
PH value | IS-456 | Once Initially thereafter once in a month . | |
Cement | Material Test Certificates | Check batch no. | Every Lot after receiving at site |
Compressive strength | IS-4031 part- VI | Every batch received at site. | |
Chemical Analysis | IS-4032 | Every batch received at site. | |
Fineness (Blaine air permeability method) | IS-4031 part- I | Every batch received at site. | |
Initial and final setting time | IS-4031 part- V | Every Batch received at site. | |
Consistency of cement | IS-4031 Part-IV | Every Batch received at site. | |
Soundness | IS-4031 part- III | Every batch received at site. | |
Admixture | Raw material test certificates | As per IS 9103 | Every lot of sample |
Relative density,pH value, field trial,solid content, bleeding percentage | Every Lot of sample | ||
Air Content | Every lot of sample | ||
Concrete | Slump test,temperature of concrete | IS-456, IS-1199 | As required by Engineer (Concrete of Each Transit Mixer should be checked prior to pour at site) |
Compressive strength (each test sample compressing of 6 cubes of 15 CM size) | IS-516,1199,456 | As per Is 456:2000 | |
IS 456-2000 | The cube samples shall be taken for each grade of concrete for following daily concrete quantity | ||
Chloride and sulphate content | IS-456 | In the beginning and with change of any source . | |
Setting Time of concrete | IS-8142 | Once in a month for each grade of concrete and each different brand of cement during production and at the time of approval of mix design | |
Air content of concrete | IS 1199 | Once in a day | |
Permeability of concrete | IS-3085 | Once in a month for each grade of concrete | |
Reinforcement | Rolling Margin | IS-1786-1985 | Each lot (client Supply Material) |
Steel | Chemical | IS-1786-1985 | Every lot. |
Physical | IS-1786-1985 | Every lot. | |
Bricks | Water absorption | IS-3495,1077 and tech spec. | Once for each stack and Brand of 10000 nos. |
Visual and Dimensions | IS-1077 and tech spec. | Once for each stack and Brand of 10000 nos. | |
Efflorescence | Tech. Spce. | Once for each stack and Brand of 10000 nos. | |
compressive strength | IS-1077 and tech spec. | Once for each stack and Brand of 10000 nos. | |
Batching plant | Calibration | IS- 4925/4926/456 | Once in a month. |
Storage and stacking of materials. | Specify code and spec no. | Daily | |
Admixture mixing proportion and review of manufacturer’s spec. | Daily | ||
Review of batch card and register. | Daily | ||
Temperature of concrete | Daily as per requirement or twice in a day | ||
Cube test for 7 days and 28 days. | Regularly | ||
Tiles, Doors, Window, Paint, Plumbing Materials, Bolts etc all incoming maerials. | MTC | Specification | Each lot |
Calibration | Calibration of test equipment | As per frequency set in Laboratory Manual | |
NCR | Control of nonconforming product | On occurrence of Nonconformity | |
Notification to customer | as and when require | On receipt of non-conforming material of customer / client |