Particular of Works

Cost in Rupees

Mode of Measurement


 

 

 1

New road CONSTRUCTION 3.75 M WITHOUT SHOULDERS

79,28,665.00

Per KM

 2

New road CONSTRUCTION 5.5 M WITHOUT SHOULDERS

1,16,28,705.00

Per KM

 3

New road CONSTRUCTION 7.0 M WITHOUT SHOULDERS

1,48,00,171.00

Per KM

 4

Renewal 3.75 M BM and BC

29,83,925.00

Per KM

 5

Renewal 5.5 M BM and BC

43,76,422.00

Per KM

 6

Renewal 7.0M BM and BC

55,69,991.00

Per KM

 7

Renewal 3.75 M BM and Carpet Sealcoat

24,59,795.00

Per KM

 8

Renewal 5.5 M BM and Carpet Sealcoat

36,07,698.00

Per KM

 9

Renewal 7.0 M BM and Carpet Sealcoat

45,91,615.00

Per KM

 10

Renewal 3.75 M MPM and Carpet Sealcoat

22,54,314.00

Per KM

 11

Renewal 5.5 M MPM and Carpet Sealcoat

33,06,325.00

Per KM

 12

Renewal 7.0 M MPM and Carpet Sealcoat

42,08,050.00

Per KM

 13

WIDENING CONSTRUCTION 3.75 M TO 5.5 M WITHOUT SHOULDERS

40,69,006.00

Per KM

 14

WIDENING CONSTRUCTION 5.5 M TO 7.0 M WITHOUT SHOULDERS

34,87,718.00

Per KM

 15

WIDENING CONSTRUCTION 7.0 M TO 10 M WITHOUT SHOULDERS

69,75,436.00

Per KM

 16

Pothole Filling upto 75 mm with MPM only

321.00

Per sq.m

 17

Pothole Filling upto 150 mm with MPM only

642.00

Per sq.m

 18

Pothole Filling upto 50 mm with BM only

376.00

Per sq.m

 19

Pothole Filling upto 150 mm with BM only

1,087.00

Per sq.m

 20

Pothole Filling upto 150 mm on OGC road with MPM and Grade 1 material

479.00

Per sq.m

 21

Pothole Filling upto 300mm on OGC road with MPM and Grade 1 material

877.00

Per sq.m

 22

Pothole Filling upto 150 mm on OGC road with BM and Grade 1 material

634.00

Per sq.m

 23

Pothole Filling upto 300 mm on OGC road with BM and Grade 1 material

992.00

Per sq.m

 