Tentative Road Works costs as per SSR 2022-23

Tentative Road Works costs as per SSR 2022-23

ESTIMATED COST FOR RENEWAL / WIDENING / REBUILT / C D WORK & MINOR BRIDGE
प्रति किमी दर
Estimated Cost based on Current SSR/WEF: 25/7/2022 (SSR-2022-23)
NoRoad Category Width of Road Rate/KM (Lakh) Including 18% GST, 3% Contengencies & 1% Labour & Road Safty ChargesTotal Provide CrustScope of Work
12345
Rebuilt work for B.C.Portion ( CBR 3% TO 5 %)
1MDR3.75125350 MM200 mm Earthwork, 300 mm Cement Treated Soil Sub Base.(CTSB), 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.5205
3MDR / SH7255
1MDR3.7595350 MM200 mm Earthwork , 300 mm Lime Stabilisation for Improving Subgrade , 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.5125
3MDR / SH7155
1MDR3.75100450 MM300 mm Cement Treated Soil Sub Base.(CTSB), 100 mm WMM, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.5135
3MDR / SH7165
1MDR3.7595350 MM200 mm CTSB, 100 mm CTB, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Tharmoplastic Paint, Road Furniture etc.
2MDR / SH5.5125
3MDR / SH7158
Renewal work
1MDR3.754575 MMSite Cleaning, Picking, Open Exavated Gutter, 75 mm MPM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.560
3MDR / SH773
4SH10100
1MDR3.7562100 MMSite Cleaning, Picking, Open Exavated Gutter, 50 mm MPM, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.585
3MDR / SH7104
4SH10143
1MDR3.757080 MMSite Cleaning, Picking, Open Exavated Gutter, 50 mm DBM, 30 mm BC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.595
3MDR / SH7115
4SH10160
Rebuilt work
1MDR3.75180450 MMSite Cleaning, Open Exavated Gutter, Earthwork, 150 mm GSB, 150 mm GR-I, 75 mm GR-II, 75 mm MPM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.5205
3MDR / SH7228.5
4SH10270
1MDR3.75172475 MMSite Cleaning, Open Exavated Gutter, Earthwork, 150 mm GSB, 150 mm GR-I, 75 mm GR-II, 50 mm MPM, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder,Road Furniture etc.
2MDR / SH5.5203.5
3MDR / SH7231
4SH10285
1MDR3.75169480 MMSite Cleaning, Open Exavated Gutter, Earthwork, 150 mm GSB, 250 mm WMM, 50 mm DBM, 30 mm BC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.5199
3MDR / SH7225
4SH10276.5
Widening work
1MDR / SH3.75 TO 5.50148450 MMSite Cleaning, Open Exavated Gutter, Earthwork, 150 mm GSB, 150 mm GR-I, 75 mm GR-II, 75 mm MPM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.50 TO 7.00159
1MDR / SH3.75 TO 5.50172475 MMSite Cleaning, Open Exavated Gutter, Earthwork, 150 mm GSB, 150 mm GR-I, 75 mm GR-II, 50 mm MPM, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.50 TO 7.00188.5
3SH7.00 TO 10.00237.84
1MDR / SH3.75 TO 5.50167480 MMSite Cleaning, Open Exavated Gutter, Earthwork, 150 mm GSB, 250 mm WMM, 50 mm DBM, 30 mm BC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.50 TO 7.00182.5
3SH7.00 TO 10.00229
C.C.Road
1MDR3.75213.5600 MMSite Cleaning, 150 mm GSB, 150 mm DLC, M-40 - 300 mm PQC, HM Side Shoulder, Road Furniture etc.
2MDR / SH5.5279
3MDR / SH7345.5
Built up Drain
11.50 m WidthPer Running Meter20000.00 / RmtM-20Site Cleaning, Exavation, 80 mm Soiling, M-10 P.C.C., M-20 Head Wall & Foundation , M-20 Slab, TMT, Weep Hole etc.
PCC Return Wall
12.50 m HightPer Running Meter55000.00 / RmtM-25Site Cleaning, Exavation, M-10 P.C.C., M-25 Wall & Foundation ,Weep Hole, Filter Media & Expansion Joint etc.
RCC Return Wall
25.00 m HightPer Running Meter450000.00 / RmtM-30Site Cleaning, Exavation, M-15 R.C.C., M-30 Wall & Foundation ,Steel , Weep Hole, Filter Media & Expansion Joint etc.
C.D.Work
1STATE HIGHWAY (12.00 M. WIDTH)1 Vent 1200 mm9.5M-20Site Cleaning, Exavation, 80 mm Soiling, M-10 P.C.C., M-20 Face Wall , NP-3 Pipe, Back Filling etc.
22 Vent 1200 mm13.5
33 Vent 1200 mm17.5
44 Vent 1200 mm21.5
55 Vent 1200 mm25.5
1MAJOR DISTRICT ROAD (10.00 M. WIDTH)1 Vent 1200 mm8M-20Site Cleaning, Exavation, 80 mm Soiling, M-10 P.C.C., M-20 Face Wall , NP-3 Pipe, Back Filling etc.
22 Vent 1200 mm12
33 Vent 1200 mm16
44 Vent 1200 mm20
55 Vent 1200 mm24
1OTHER DISTRICT ROAD & VILLAGE ROAD (7.50 M. WIDTH)1 Vent 1200 mm6M-20Site Cleaning, Exavation, 80 mm Soiling, M-10 P.C.C., M-20 Face Wall , NP-3 Pipe, Back Filling etc.
22 Vent 1200 mm9
33 Vent 1200 mm12
44 Vent 1200 mm15
55 Vent 1200 mm18
Minor Bridge Work
1SH (12.00 M)--10.00 Lakh/ M.Cost includeing Both side 50 m. Approches with Diversion.
2MDR(10.00 M)--8.50 Lakh/ M.

 

 

Particular of Works

Cost in Rupees

Mode of Measurement


 

 

 1

New road CONSTRUCTION 3.75 M WITHOUT SHOULDERS

79,28,665.00

Per KM

 2

New road CONSTRUCTION 5.5 M WITHOUT SHOULDERS

1,16,28,705.00

Per KM

 3

New road CONSTRUCTION 7.0 M WITHOUT SHOULDERS

1,48,00,171.00

Per KM

 4

Renewal 3.75 M BM and BC

29,83,925.00

Per KM

 5

Renewal 5.5 M BM and BC

43,76,422.00

Per KM

 6

Renewal 7.0M BM and BC

55,69,991.00

Per KM

 7

Renewal 3.75 M BM and Carpet Sealcoat

24,59,795.00

Per KM

 8

Renewal 5.5 M BM and Carpet Sealcoat

36,07,698.00

Per KM

 9

Renewal 7.0 M BM and Carpet Sealcoat

45,91,615.00

Per KM

 10

Renewal 3.75 M MPM and Carpet Sealcoat

22,54,314.00

Per KM

 11

Renewal 5.5 M MPM and Carpet Sealcoat

33,06,325.00

Per KM

 12

Renewal 7.0 M MPM and Carpet Sealcoat

42,08,050.00

Per KM

 13

WIDENING CONSTRUCTION 3.75 M TO 5.5 M WITHOUT SHOULDERS

40,69,006.00

Per KM

 14

WIDENING CONSTRUCTION 5.5 M TO 7.0 M WITHOUT SHOULDERS

34,87,718.00

Per KM

 15

WIDENING CONSTRUCTION 7.0 M TO 10 M WITHOUT SHOULDERS

69,75,436.00

Per KM

 16

Pothole Filling upto 75 mm with MPM only

321.00

Per sq.m

 17

Pothole Filling upto 150 mm with MPM only

642.00

Per sq.m

 18

Pothole Filling upto 50 mm with BM only

376.00

Per sq.m

 19

Pothole Filling upto 150 mm with BM only

1,087.00

Per sq.m

 20

Pothole Filling upto 150 mm on OGC road with MPM and Grade 1 material

479.00

Per sq.m

 21

Pothole Filling upto 300mm on OGC road with MPM and Grade 1 material

877.00

Per sq.m

 22

Pothole Filling upto 150 mm on OGC road with BM and Grade 1 material

634.00

Per sq.m

 23

Pothole Filling upto 300 mm on OGC road with BM and Grade 1 material

992.00

Per sq.m

 