🛣 EPC Schedules Preparation Overview
For any EPC (Engineering, Procurement, and Construction) work, preparing accurate schedules is crucial. Incorrect schedules may lead to time extensions, cost variations, and contractual issues. This requires detailed data collection from the Detailed Project Report (DPR) and field investigations.
graph LR
A[Traditional Modes of Project Execution] --> B[Item-rate]
A --> C[Percentage-rate]
A --> D[BOT Build-Operate-Transfer]
A --> E[Annuity]
A --> F[Hybrid Annuity]
B:::mode --> B1[Only rates and units of items mentioned]
B --> B2[Payment based on actual quantities
measured and certified] C:::mode --> C1[Quantities, rates, and units of items
are mentioned from drawings] C --> C2[Payment based on actual measured quantities] D:::mode --> D1[Private sector constructs, operates, and collects tolls/fees] D --> D2[No cost to government for construction] E:::mode --> E1[Project cost paid as annual payments - Annuity] E --> E2[Payments made by host government] F:::mode --> F1[Project cost partly paid during progress] F --> F2[Remaining cost paid as annual annuity by government]
measured and certified] C:::mode --> C1[Quantities, rates, and units of items
are mentioned from drawings] C --> C2[Payment based on actual measured quantities] D:::mode --> D1[Private sector constructs, operates, and collects tolls/fees] D --> D2[No cost to government for construction] E:::mode --> E1[Project cost paid as annual payments - Annuity] E --> E2[Payments made by host government] F:::mode --> F1[Project cost partly paid during progress] F --> F2[Remaining cost paid as annual annuity by government]
graph TD
A[EPC Tender] --> B[Articles]
A --> C[Schedules]
B --> D[27]
C --> E[18]
D --> AA[Core legal framework]
E --> AB[Project Information-Annexures]
graph TD
A[Articles] --> B[Risk Allocation]
A --> C[Rights]
A --> D[Responsibilities]
A --> E[procedures]
C --> AA[Contractors]
C --> AB[Authority]
D --> AC[Contractors]
D --> AD[Authority]
graph LR
A[Articles] --> A1[Definitions and Interpretation]
A --> A2[Scope of the Project]
A --> A3[Obligations of the Authority]
A --> A4[Obligations of the Contractor]
A --> A5[Representations and Warranties]
A --> A6[Disclaimer]
A --> A7[Performance Security]
A --> A8[Right of Way]
A --> A9[Utilities and Trees]
A --> A10[Design and Construction of the Project Highway]
A --> A11[Quality Assurance, Monitoring and Supervision]
A --> A12[Completion Certificate]
A --> A13[Change of Scope]
A --> A14[Maintenance]
A --> A15[Supervision and Monitoring during Maintenance]
A --> A16[Traffic Regulation]
A --> A17[Defect Liability]
A --> A18[Authority’s Engineer]
A --> A19[Payments]
A --> A20[Insurance]
A --> A21[Force Majeure]
A --> A22[Suspension of Contractor’s Rights]
A --> A23[Termination]
A --> A24[Assignment and Charges]
A --> A25[Liability and Indemnity]
A --> A26[Dispute Resolution]
A --> A27[Miscellaneous]
graph LR
A[Schedules] --> A1[Schedule-A Site of the Project Highway]
A --> A2[Schedule-B Development of the Project Highway]
A --> A3[Schedule-C Project Facilities]
A --> A4[Schedule-D Specifications and Standards refers to MoRTH Specifications, IRCCodes, etc.]
A --> A5[Schedule-E Maintenance Requirements]
A --> A6[Schedule-F Applicable Permits]
A --> A7[Schedule-G Form Of Bank Guarantee]
A --> A8[Schedule-H Contract Price Weightages]
A --> A9[Schedule-I Drawings]
A --> A10[Schedule-J Project Completion Schedule]
A --> A11[Schedule-K Tests on Completion]
A --> A12[Schedule-L Completion Certificate]
A --> A13[Schedule-M Payment Reduction for Non-Compliance]
A --> A14[Schedule-N Selection of Authority’s Engineer]
A --> A15[Schedule-O Forms of Payment Statements]
A --> A16[Schedule-P Insurance]
A --> A17[Schedule-Q Tests on Completion of Maintenance Period]
A --> A18[Schedule-R Taking Over Certificate]
📋 Required Schedules & Their Inputs
🔹 Schedule A: Existing Road Information
Information to be Given | Data Required from Field / DPR |
---|---|
Chainage-wise ROW of existing road | Cadastral / Village Maps |
Road width, surface type, shoulders | Inventory Survey of Road |
Existing structures: Bridges, Culverts, ROBs, etc. | Inventory Survey of Structures |
Bus bays, truck lay-byes | Inventory Survey |
Roadside drains | Inventory Survey |
Junction details (type, category, width) | Inventory Survey of Junctions |
Existing bypasses | Inventory Survey |
Existing vs. Design Chainages | Alignment Design |
Overhead/Underground utilities | Utility Inventory Survey |
Plan & Profile of Road | Topographical Survey & Alignment Design |
Forest Land | Inventory Survey |
🔹 Schedule B: Proposed Improvements
Information to be Given | Data Required |
---|---|
Built-up stretches and applicable TCS | Alignment Design, ROW info |
Design constraint stretches | Alignment Design, BC Soil Inventory |
Widening, Reconstruction, Raising segments | Full Improvement Proposal |
Non-scope stretches | Inventory & Alignment Design |
Junctions to be improved | Junction Inventory |
CD Works, Bridges improvement | Chainage-wise Structure Details |
Proposed pavement type (BT/Concrete) | Traffic & Axle Load Survey |
Proposed drains (earthen/CC/built-up) | Chainage-wise Drainage Plan |
Roadside furniture (signage, markings) | Signage Plan |
Protection works (retaining walls, barriers) | Plan & Profile |
Typical Cross Sections (TCS) | Widening, Reconstruction, Raising Plans |
🔹 Schedule C: Project Facilities
Information | Requirement |
---|---|
Street lights, Bus bays/shelters, Signage, Pedestrian facilities | Based on Inventory and Development Proposals |
🔹 Schedule D: Specifications and Standards
Information | Requirement |
---|---|
IRC:SP-73 Guidelines | As per type of Project appropriate standards are to be given |
Deviation from standard Guidelines | To be explicitly listed for Contractor |
🔹 Schedule E: Maintenance Requirements
- Post-construction maintenance duration (typically 5–10 years).
- Performance-based criteria: ride quality, rutting, pothole-free surface.
- Routine and periodic maintenance responsibilities.
- Maintenance penalties for non-compliance.
🔹 Schedule F: Applicable Permits
🔹 Schedule G: Form Of Bank Guarantee
🔹 Schedule H: Payment Schedule
Component | Requirement |
---|---|
Road, Structure, Drains, Junctions, Walls, Signage, Protection Works | Percentage-based on Cost Estimate |
🔹 Schedule I: Drawings
🔹 Schedule J: Project Completion Schedule
🔹 Schedule K: Tests on Completion
🔹 Schedule L: Completion Certificate
🔹 Schedule M: Payment Reduction for Non-Compliance
🔹 Schedule N: Selection of Authority’s Engineer
🔹 Schedule O: Forms of Payment Statements
🔹 Schedule P: Insurance
🔹 Schedule Q: Tests on Completion of Maintenance Period
🔹 Schedule R: Taking Over Certificate
📌 Conclusion
A comprehensive Improvement Proposal is to be developed based on:
- Road, structures, junctions, utilities inventory
- Trial pits, geotechnical investigations
- Traffic & axle load survey
- Plan & Profile development
- Pavement and protection design
Only then can a detailed cost estimate and all required Schedules (A to H) be finalized.
- Road, structures, junctions, utilities inventory
- Trial pits, geotechnical investigations
- Traffic & axle load survey
- Plan & Profile development
- Pavement and protection design
Only then can a detailed cost estimate and all required Schedules (A to H) be finalized.
0 Comments
If you have any doubts, suggestions , corrections etc. let me know