YogiPWD

EPC Schedules Preparation Overview

EPC Schedules Preparation

🛣 EPC Schedules Preparation Overview

For any EPC (Engineering, Procurement, and Construction) work, preparing accurate schedules is crucial. Incorrect schedules may lead to time extensions, cost variations, and contractual issues. This requires detailed data collection from the Detailed Project Report (DPR) and field investigations.
graph LR A[Traditional Modes of Project Execution] --> B[Item-rate] A --> C[Percentage-rate] A --> D[BOT Build-Operate-Transfer] A --> E[Annuity] A --> F[Hybrid Annuity] B:::mode --> B1[Only rates and units of items mentioned] B --> B2[Payment based on actual quantities
measured and certified] C:::mode --> C1[Quantities, rates, and units of items
are mentioned from drawings] C --> C2[Payment based on actual measured quantities] D:::mode --> D1[Private sector constructs, operates, and collects tolls/fees] D --> D2[No cost to government for construction] E:::mode --> E1[Project cost paid as annual payments - Annuity] E --> E2[Payments made by host government] F:::mode --> F1[Project cost partly paid during progress] F --> F2[Remaining cost paid as annual annuity by government]
graph TD A[EPC Tender] --> B[Articles] A --> C[Schedules] B --> D[27] C --> E[18] D --> AA[Core legal framework] E --> AB[Project Information-Annexures]
graph TD A[Articles] --> B[Risk Allocation] A --> C[Rights] A --> D[Responsibilities] A --> E[procedures] C --> AA[Contractors] C --> AB[Authority] D --> AC[Contractors] D --> AD[Authority]
graph LR A[Articles] --> A1[Definitions and Interpretation] A --> A2[Scope of the Project] A --> A3[Obligations of the Authority] A --> A4[Obligations of the Contractor] A --> A5[Representations and Warranties] A --> A6[Disclaimer] A --> A7[Performance Security] A --> A8[Right of Way] A --> A9[Utilities and Trees] A --> A10[Design and Construction of the Project Highway] A --> A11[Quality Assurance, Monitoring and Supervision] A --> A12[Completion Certificate] A --> A13[Change of Scope] A --> A14[Maintenance] A --> A15[Supervision and Monitoring during Maintenance] A --> A16[Traffic Regulation] A --> A17[Defect Liability] A --> A18[Authority’s Engineer] A --> A19[Payments] A --> A20[Insurance] A --> A21[Force Majeure] A --> A22[Suspension of Contractor’s Rights] A --> A23[Termination] A --> A24[Assignment and Charges] A --> A25[Liability and Indemnity] A --> A26[Dispute Resolution] A --> A27[Miscellaneous]
graph LR A[Schedules] --> A1[Schedule-A Site of the Project Highway] A --> A2[Schedule-B Development of the Project Highway] A --> A3[Schedule-C Project Facilities] A --> A4[Schedule-D Specifications and Standards refers to MoRTH Specifications, IRCCodes, etc.] A --> A5[Schedule-E Maintenance Requirements] A --> A6[Schedule-F Applicable Permits] A --> A7[Schedule-G Form Of Bank Guarantee] A --> A8[Schedule-H Contract Price Weightages] A --> A9[Schedule-I Drawings] A --> A10[Schedule-J Project Completion Schedule] A --> A11[Schedule-K Tests on Completion] A --> A12[Schedule-L Completion Certificate] A --> A13[Schedule-M Payment Reduction for Non-Compliance] A --> A14[Schedule-N Selection of Authority’s Engineer] A --> A15[Schedule-O Forms of Payment Statements] A --> A16[Schedule-P Insurance] A --> A17[Schedule-Q Tests on Completion of Maintenance Period] A --> A18[Schedule-R Taking Over Certificate]

📋 Required Schedules & Their Inputs

🔹 Schedule A: Existing Road Information

Information to be GivenData Required from Field / DPR
Chainage-wise ROW of existing roadCadastral / Village Maps
Road width, surface type, shouldersInventory Survey of Road
Existing structures: Bridges, Culverts, ROBs, etc.Inventory Survey of Structures
Bus bays, truck lay-byesInventory Survey
Roadside drainsInventory Survey
Junction details (type, category, width)Inventory Survey of Junctions
Existing bypassesInventory Survey
Existing vs. Design ChainagesAlignment Design
Overhead/Underground utilitiesUtility Inventory Survey
Plan & Profile of RoadTopographical Survey & Alignment Design
Forest LandInventory Survey

🔹 Schedule B: Proposed Improvements

Information to be GivenData Required
Built-up stretches and applicable TCSAlignment Design, ROW info
Design constraint stretchesAlignment Design, BC Soil Inventory
Widening, Reconstruction, Raising segmentsFull Improvement Proposal
Non-scope stretchesInventory & Alignment Design
Junctions to be improvedJunction Inventory
CD Works, Bridges improvementChainage-wise Structure Details
Proposed pavement type (BT/Concrete)Traffic & Axle Load Survey
Proposed drains (earthen/CC/built-up)Chainage-wise Drainage Plan
Roadside furniture (signage, markings)Signage Plan
Protection works (retaining walls, barriers)Plan & Profile
Typical Cross Sections (TCS)Widening, Reconstruction, Raising Plans

🔹 Schedule C: Project Facilities

InformationRequirement
Street lights, Bus bays/shelters, Signage, Pedestrian facilitiesBased on Inventory and Development Proposals

🔹 Schedule D: Specifications and Standards

InformationRequirement
IRC:SP-73 GuidelinesAs per type of Project appropriate standards are to be given
Deviation from standard GuidelinesTo be explicitly listed for Contractor

🔹 Schedule E: Maintenance Requirements

🔹 Schedule F: Applicable Permits


🔹 Schedule G: Form Of Bank Guarantee


🔹 Schedule H: Payment Schedule

ComponentRequirement
Road, Structure, Drains, Junctions, Walls, Signage, Protection WorksPercentage-based on Cost Estimate

🔹 Schedule I: Drawings


🔹 Schedule J: Project Completion Schedule


🔹 Schedule K: Tests on Completion


🔹 Schedule L: Completion Certificate


🔹 Schedule M: Payment Reduction for Non-Compliance


🔹 Schedule N: Selection of Authority’s Engineer


🔹 Schedule O: Forms of Payment Statements


🔹 Schedule P: Insurance


🔹 Schedule Q: Tests on Completion of Maintenance Period


🔹 Schedule R: Taking Over Certificate


📌 Conclusion

A comprehensive Improvement Proposal is to be developed based on:
- Road, structures, junctions, utilities inventory
- Trial pits, geotechnical investigations
- Traffic & axle load survey
- Plan & Profile development
- Pavement and protection design

Only then can a detailed cost estimate and all required Schedules (A to H) be finalized.

Post a Comment

0 Comments