Understanding Highway road project Contract Models: BOT, TOT, HAM & EPC
India's highway sector doesn't run on just one funding/contract model. Government authorities uses different approaches depending on traffic potential, financial viability, and the government's priorities. Here's a simplified explanation:
EPC - Engineering, Procurement & Construction
Government funds 100% of the project.
Contractor is only responsible to design & build the road.
No revenue or traffic risk for the contractor.
After construction, O&M is handled by the Authority.
Best when: traffic is uncertain or the project is of strategic importance.
BOT - Build, Operate, Transfer
Private company finances + builds + maintains the road.
Two variants:
- BOT (Toll): Concessionaire collects tolls directly → bears traffic risk.
- BOT (Annuity): Concessionaire gets fixed payments (annuities) from Authority → no traffic risk.
Best when: traffic is predictable (Toll) or government prefers fixed payments (Annuity).
Traffic Revenue (BOT Toll):
\[ R = \sum_{t=1}^{n} (V_t \times T_r) \times (1+g)^t \] where \( V_t \) = traffic volume in year \( t \), \( T_r \) = toll rate, \( g \) = traffic growth rate.Annuity Payment (BOT Annuity):
\[ A = \frac{P \cdot r}{1 - (1+r)^{-n}} \] where \( P \) = project cost, \( r \) = discount/interest rate, \( n \) = number of annuity periods.HAM - Hybrid Annuity Model
40% of cost paid by Government during construction.
60% of cost invested by private party (via debt & equity).
Private player gets semi-annual annuities + O&M payments for ~15 years.
No traffic risk for private party; only construction & maintenance performance risk.
Best when: balance is needed between EPC's safety and BOT's efficiency.
Government Share:
\[ G = 0.4 \times C \]Private Share:
\[ P = 0.6 \times C \] where \( C \) = total project cost.TOT - Toll, Operate, Transfer
Only for operational brownfield highways.
Investor pays upfront concession fee to Government.
Gets rights to collect tolls & maintain road for ~30 years.
Govt uses upfront money to fund new highway projects.
Best when: government wants to monetise completed assets and recycle funds.
Net Present Value (NPV) of TOT:
\[ NPV = \sum_{t=1}^{n} \frac{CF_t}{(1+r)^t} - F \] where \( CF_t \) = expected cashflow in year \( t \), \( r \) = discount rate, \( F \) = upfront concession fee.
1 Comments
Excellent post on procurement systems. BidHelp helps simplify the entire application process and ensures complete document compliance for businesses. Check more details here
ReplyDeleteprocurement
Thanks for the valuable content.
If you have any doubts, suggestions , corrections etc. let me know